Replies: 1 comment
-
The operation modle has size-minimum, size-multiple and size-maximum fields to control the allowed size of the production orders. |
Beta Was this translation helpful? Give feedback.
0 replies
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
-
I configure the operation material that adopted the gross die as 56.1, and executed a plan. I found the planner used 1 WF for fulfilling 43.4 dies. Just wondering know how can config that let the planner shows the original quantities as 0.773, not rounding up to 1?
Beta Was this translation helpful? Give feedback.